Kype Muir Extension - Kype Muir Extension Construction

Construction timeline and activity

We have had some delays which has meant the program has started later than expected, but we still anticipate finishing at the time originally planned in December 22.

During the construction period there will be a varying amount of traffic movements. Our plans for abnormal loads and managing the increased volume of visits during the construction have been shared with the local authorities to produce the Traffic Management Plan.

Our updated program anticipates that the average daily movements to be in line with the original estimates, and that its peak should sit between 80-120 on average.

Turbine Delivery Route

Port of entry at King George V Docks in Glasgow

 

Route takes Kings Inch Drive, M8, M74 and finally the B743 from where the vehicles will access the windfarm.

Temporary Footpath Closure

Sign displayed at entrance to site

During the construction process, and for the safety of the local community, one of the core paths in the area will be closed. We will place communication for the local community at the entrance to the path, notify local community councils, the local newspaper, and local websites relevant to the monument and footpaths. We will also permanently upgrade a section of the path which will form part of the access tracks for the site which the public will be free to use once the construction has ended.

Alternative routes to the monument will be shown at the site.

The community manager for this project will be Robin Winstanley.

To get in touch and find out more:

Tel: 07714702323

Email: kypemuir@banksgroup.co.uk

You can stay in touch and ask questions through your local community council

If you or your community would like to find out more about community grants through the Kype Muir Community Partnership, please visit:

Kype Muir Wind Farm Community Fund

Get in touch

We welcome your feedback

Whether you wish to tell us that we have done something really well or that we could have done something better we value your feedback.

It helps us to shape the way we operate and to continually improve our performance. It is very much part of our development with care approach.

Back to Project

Support this Project

Thank you for supporting our Kype Muir Extension Construction proposal. Please enter your details in the form below and let us know your reasons for supporting Kype Muir Extension Construction in the free text box below. Some examples are:

The information in this form will be emailed to the Banks Group and may be passed on to the relevant planning officer.

Registered office: Inkerman House, St John's Road, Meadowfield, Durham, DH7 8XL

Registered in England number 2267400. VAT registration number 569 3236 14

© 2021 Banks Group. All rights reserved.