To view our public webinar that took place on Tuesday 17 November 2020, at 19.00hrs, please click on the following YouTube link: www.youtube.com/Banks Group webinar on Bowesfield Flexible Energy Park

To simply view the slides presented in our public webinar on Tuesday 17 November 2020, at 19.00hrs, please see: Bowesfield Flexible Energy Park, webinar slide pack, November 2020

Please click the following link to see a copy of the Webinar Q&A document, Nov 2020

Please click the following link to see a copy of the Bowesfield Energy Flexibility Park webinar invitation leaflet, October 2020

We are proposing to develop an innovative project to build and run a natural gas / hydrogen ‘peaker’ plant and an electricity storage battery on the Bowesfield Crescent Industrial Estate, Stockton-on-Tees.

SUPPORT Bowesfield Flexible Energy Park

Support Bowesfield Flexible Energy Park

The information in this form will be emailed to the Banks Group and may be passed on to the relevant planning officer.

The Banks Group would like to use your contact details to update you on the progress of the project from time to time. If you would like to be kept up to date please tick this box. You can opt out at any time later on.

Local authority: Stockton-on-Tees Borough Council

Postcode of offices near to the site: TS18 3BL

Size: c0.5 hectares (c1.2 acres)

History: The riverside site formerly had a foundry on it and the Teesside Development Corporation 1987 to 1998 extracted clay from the site.

Project description: The proposal is for The Banks Group to build and run a gas / hydrogen peaker plant on the Bowesfield industrial estate, Stockton-on-Tees. The type of “peaking power plant”, (also known as a “peaker plants”), we are seeking to install at Bowesfield Crescent Industrial Estate, is a power plant that will run on either natural gas or hydrogen, to generate electricity. Peaker plants are very good at handling short-term, sudden surges in electricity demand. In this way they help balance supply with demand – in short they help balance the grid.

Co-located next to the peaker plant will be a battery that will be charged by power from the National Grid. This electricity stored in the battery can also then be released to the National Grid at times of peak demand.

All being well we are aiming to have this flexible energy park be operational by Autumn 2022.

Background:

Local energy storage and generation: The shift underway towards the de-centralisation of the National Grid, in which energy distribution will be managed in smaller, more localised, grids rather than the large-scale network operator system currently in place, will see storage capacity in certain areas of the UK increase. Energy storage will play a key role the smart, flexible and decarbonised future energy system.

Economic benefits:

• Due to the nature of combined peaker and battery storage plants they have the ability to generate electricity when the cost of their fuel is low. The energy they generate is released to the grid at times of peak demand and high price. This makes them economically viable, able to create local wealth and jobs.

Social benefits:

• Access to electricity is widely regarded as a prerequisite for an appropriate / decent standard of living and social integration.

• Ensuring the sufficient provision of electricity generated by economically, environmentally and socially acceptable means continues to be an important objective for policymakers around the world. Peaker plants have a valuable part to play to balancing the grid.

Environmental benefits:

• Natural gas peaker plants do not produce emissions all of the time, because they do not run all of the time. As the name implies, they run when the network experiences a peak in demand and there is not enough generation to meet that demand.

• Due to their very nature as assets that serve loads quickly and locally to meet network demand, peaker plants are often also located in more densely populated areas than other types of thermal power plant.

Get in touch

We welcome your feedback

Whether you wish to tell us that we have done something really well or that we could have done something better we value your feedback.

It helps us to shape the way we operate and to continually improve our performance. It is very much part of our development with care approach.

Back to Project

Support this Project

Thank you for supporting our Bowesfield Flexible Energy Park proposal. Please enter your details in the form below and let us know your reasons for supporting Bowesfield Flexible Energy Park in the free text box below. Some examples are:

The information in this form will be emailed to the Banks Group and may be passed on to the relevant planning officer.

Registered office: Inkerman House, St John's Road, Meadowfield, Durham, DH7 8XL

Registered in England number 2267400. VAT registration number 569 3236 14

© 2021 Banks Group. All rights reserved.